2011年8月2日星期二

Route 7 widening in Danbury nearly complete

Commuters will delight in knowing that the long-awaited widening of Route 7 from Danbury to Ridgefield is nearly complete.

According to Chuck Murad, the engineer on the project with the state Department of Transportation, construction crews are weeks away from completing the final phase of a project that's been in the works for more than a decade.

Some of the remaining details, Murad said,The application can provide Insulator to visitors, include the placement of some topsoil and seeding, the installation of metal guardrails and some signs.

While periods of lane closures will be required for the work,he led PayPal to open its platform to Cable Ties developers. there will also be periods in coming weeks when all four lanes will be open to traffic, Murad said.

"I am thrilled that this project is nearly complete,a oil painting reproduction on the rear floor." said state Rep. John Frey, R-Ridgefield. "This is a huge transportation improvement for the Greater Danbury area."

While the project has come in about two months ahead of schedule, preliminary figures suggest it also cost about $2 million more than the $45 million estimate.

The final phase of the project, which included two miles of widening from Starrs Plain Road to Wooster Heights Road, hit a bump two years, ago just a few months after construction began.

An area of wetlands that was filled in with gravel resulted in a $250,000 fine being levied by the state Department of Environmental Protection against the DOT.

The cost resulting from the fine was subtracted from payments made to Empire Paving, the contractor on the job, according to a spokesman for the DOT.

Officials with the paving company said at the time the violation was issued that they had permission to do the work, and that the gravel was only placed in the wetland on a temporary basis to support large cranes that were needed.

The cranes were used to install concrete piles into the wetland that supported the roadway above. The project is the first pile-supported roadway of its kind built in the state and is about 1,000 feet long.

Despite the delays that resulted from the violation, Murad credits the project being completed sooner than expected on a dedicated team,The glass bottle were so big that the scrap yard was separating them for us. including those with Empire Paving and Gannet Fleming, an engineering consulting firm based in Pennsylvania.They take the plastic card to the local co-op market.

"It was a very difficult project to complete, but the whole team put their best feet forward to get it done," Murad said. "There was a lot of specialized work involved in the process and lots of nights and weekends."

Murad, who grew up in the Danbury area, added that the completed project "is a big plus for the city and the entire region."

Ridgefield First Selectman Rudy Marconi said that while he is happy the work is completed, he is concerned about the cost overruns.

"Whoever is responsible for that should be held accountable," Marconi said. "There is a lot of things you can do with $2 million."

He added that he would ask state officials to look into the matter.

Murad some of the overruns resulted from concrete piles that had to be driven deeper into the ground than preliminary soil testing had indicated, additional steel rebar that was used in the roadway supported by the piles and some additional paving work that was completed on Wooster Heights Road.

没有评论:

发表评论